Live data from KSEB Self Services Portal (Updated: 23-12-2025 11:10-11:13 AM)
| Transformer Area | Capacity | Already Installed | Remaining | Status |
|---|---|---|---|---|
| HVDS Oxygen | 12 kW | 15 kW | 0 kW | CLOSED |
| Kumbanad Shalem Church | 85 kW | 86 kW | 0 kW | CLOSED |
| Vyduthy Bhavan | 51 kW | 70 kW | 0 kW | CLOSED |
| Kumbanad Substation | 81 kW | 80 kW | 1 kW | LAST 1 kW LEFT |
If you live in any of these areas, KSEB will NOT approve any new solar installations until the transformer is upgraded (typically 2-3 years). The only option is to apply for a different transformer area if available.
| Transformer Area | Capacity | Already Installed | Remaining | Status |
|---|---|---|---|---|
| New Hostel | 81 kW | 79.3 kW | 1.7 kW | CRITICAL |
| Madammukku | 81 kW | 73.08 kW | 1.92 kW | CRITICAL |
| Karmilaram | 129 kW | 107 kW | 2 kW | CRITICAL |
| Kanamoottil Pady | 81 kW | 78.3 kW | 2.7 kW | HIGH RISK |
Transformers with less than 5kW remaining will reach 90% capacity within 24-48 hours based on current installation rates. Once they hit 90%, no more solar installations allowed for 2-3 years.
| Transformer Area | Capacity | Already Installed | Remaining | Status |
|---|---|---|---|---|
| Kulathodu | 81 kW | 70.16 kW | 10.84 kW | MEDIUM RISK |
| Kulam | 81 kW | 61.13 kW | 19.87 kW | MEDIUM RISK |
These transformers have 1-2 weeks of capacity remaining. While not immediate emergencies, they require planning now to avoid missing the deadline.
Based on current installation rates, transformers with less than 5kW remaining will reach 90% capacity within 24-48 hours. After that, you'll have to wait 2-3 years for transformer upgrades.
Our team monitors KSEB portal every 6 hours to provide accurate capacity updates
Act NOW to secure both transformer capacity AND low-interest financing
EMI for 3kW system (10-year tenure)
Apply within 48h to secure transformer capacity
Get ₹78,000 subsidy for 3kW system through government schemes
Complete maintenance support for your solar system
Transformers filling fast - Book your system size NOW
Ideal for 2-3 BHK Homes
*After ₹78,000 Subsidy
Perfect for Large Homes/Offices
*After ₹78,000 Subsidy
⚠️ IMPORTANT: Larger systems require more transformer capacity. Check availability before choosing system size.
Available for urgent solar service visits in Pathanamthitta district
Solis Green India provides complete solar solutions for homes, shops, offices and institutions across Pathanamthitta district – including Thiruvalla, Ranni, Adoor, Kozhencherry, Pandalam, Mallappally, Elanthoor and nearby areas.
⚠️ URGENT NOTICE: Multiple KSEB transformers are at or near 100% capacity. Installation delays could mean waiting 2-3 years for transformer upgrades.
Major towns we cover for solar installation: Thiruvalla, Ranni, Adoor, Kozhencherry, Rani, Pandalam, Mallappally, Elanthoor, Konni and surrounding villages.
Check transformer capacity status for your town. Red badges indicate critical capacity situations.
Multiple transformers in Thiruvalla area at critical capacity levels. Urgent action required.
Adoor transformers at 85% capacity - approaching 90% cutoff limit.
District HQ area showing medium risk. Good time to plan before capacity fills.
Ranni area shows good capacity availability but filling steadily.
7 transformers already at 100% capacity. 6 more with less than 5kW remaining.
Once YOUR transformer reaches 90%, you'll wait 2-3 years for solar.